Concrete Patio costs $6.41 to $14.66 per sq ft in Orlando in 2026. For a 400 sq ft project, expect $2,566 – $5,864 installed, typically near $4,215. That is essentially in line with the Florida average.
Orlando concrete patio calculator
Planning estimate. Wage index applies to the labor share only; materials held at national prices. Get three written quotes.
How Orlando compares with the rest of Florida
Construction wages in Orlando average $26.37 per hour against $26.71 statewide, so pricing tracks the Florida norm closely.
Labor is about 52% of the installed cost on this type of work, and it is the part that actually moves between markets. Materials are priced by national manufacturers and barely shift, which is why the gap between metros is narrower than wage differences alone suggest.
Concrete Patio cost by project size in Orlando
| Project size | Orlando range | Typical |
|---|---|---|
| 100 sq ft | $641 – $1,466 | $1,054 |
| 200 sq ft | $1,283 – $2,932 | $2,107 |
| 300 sq ft | $1,924 – $4,398 | $3,161 |
| 400 sq ft | $2,566 – $5,864 | $4,215 |
| 600 sq ft | $3,848 – $8,796 | $6,322 |
| 800 sq ft | $5,131 – $11,728 | $8,430 |
| 1,000 sq ft | $6,414 – $14,660 | $10,537 |
| 1,500 sq ft | $9,621 – $21,990 | $15,805 |
Where the money goes
For a 400 sq ft project in Orlando at roughly $4,215, a typical bill splits like this:
| Line item | Share | Cost |
|---|---|---|
| Labor | 52% | $2,192 |
| Materials | 34% | $1,433 |
| Site prep & equipment | 8% | $337 |
| Overhead, disposal & finishing | 6% | $253 |
Orlando compared with other Florida markets
| Area | Cost per sq ft | vs Orlando |
|---|---|---|
| Miami | $6.60 – $15.08 | +3% |
| Tampa | $6.45 – $14.74 | +1% |
| Jacksonville | $6.46 – $14.77 | +1% |
| Cape Coral | $6.36 – $14.53 | −1% |
| Florida average | $6.45 – $14.75 | +1% |
Ground conditions and code in Orlando
Permits in Orlando
A residential permit for this work typically runs around $500 in Florida. Permit cost is rarely included in a contractor quote, so budget it separately and confirm scope with the Orlando building department before work begins.
Hiring in Orlando
Get three written, itemised quotes from licensed and insured contractors, each specifying the same scope and grade of material. Ask for local references and check the licence is current in Florida.
Frequently asked questions
How much does concrete patio cost in Orlando?
In 2026, concrete patio costs $6.41 to $14.66 per sq ft in Orlando. For a 400 sq ft project, the installed total typically lands between $2,566 and $5,864.
Is Orlando more expensive than the rest of Florida?
Not meaningfully. Orlando prices track the Florida average closely.
Do I need a permit in Orlando?
Most work of this type and value requires a permit. Budget around $500 in Florida and allow extra time for review in metro jurisdictions.
How do I compare quotes in Orlando?
Get three written, itemised quotes covering identical scope and materials. A bid far below the others usually signals a reduced specification rather than better value.